Articles
🔍
| No. | Published In | Article Title |
|---|---|---|
| 1 | MBJ 3rd Qtr 2002 | Can the Contractor Insist on Agreeing to Variation Costs Before Proceeding? |
| 2 | MBJ 4th Qtr 2002 | Is The Contractor Bound by His Tendered Rates if Quantities Changed? |
| 3 | MBJ 1st Qtr 2003 | Must the QS take into account signed daywork sheets? |
| 4 | MBJ 2nd Qtr 2003 | Should Retention Sum be Placed under a Separate Bank Account? |
| 5 | MBJ 3rd Qtr 2003 | When Must Retention Sum be Released and Paid? |
| 6 | MBJ 4th Qtr 2003 | What is Set-off under Construction Contracts? |
| 7 | MBJ 1st Qtr 2004 | Can Loss and/or Expense Form Part of a Variation Item? |
| 9 | MBJ 3rd Qtr 2004 | Should a Sub-contractor Sign a Sub-contract with Pay-When-Paid Clause? |
| 10 | MBJ 4th Qtr 2004 | Is Final Account Final? Circumstances allowing revisions. |
| 11 | MBJ 1st Qtr 2005 | What is Loss and/or Expense? |
| 12 | MBJ 2nd Qtr 2005 | Must the Contractor Notify the Employer/SO of its Loss and/or Expense Claim? |
| 13 | MBJ 3rd Qtr 2005 | Should additional preliminaries be evaluated on recurring costs or actual costs? |
| 14 | MBJ 4th Qtr 2005 | What is a performance bond, its Purpose and Implications? |
| 15 | MBJ 1st Qtr 2006 | What is the recent position on retention sums in Malaysia? |
| 16 | MBJ 2nd Qtr 2006 | Is the contractor obliged to apply for extension of time? |
| 17 | MBJ 3rd Qtr 2006 | Is the contractor still entitled to EOT when there is concurrent delay? |
| 18 | MBJ 4th Qtr 2006 | 'Float' in the programme of works, who owns it? |
| 19 | MBJ 1st Qtr 2007 | What are the obligations of the contractor during defect liability period? |
| 20 | MBJ 2nd Qtr 2007 | Can a contractor claim compensation for extra work with no S.O. instruction? |
| 21 | MBJ 3rd Qtr 2007 | What is a Quantum Meruit Claim? |
| 22 | MBJ 4th Qtr 2007 | Can A Letter Of Intent be Construed As An Enforceable Contract? |
| 23 | MBJ 1st Qtr 2008 | Must The Contractor Submit His Interim Payment Claims Before The SO Certifies? |
| 24 | MBJ 2nd Qtr 2008 | Is Determination of Employment and Termination of Contract the Same? |
| 25 | MBJ 3rd Qtr 2008 | Is the Late Payment a Ground For Determination or Termination? |
| 26 | MBJ 4th Qtr 2008 | What Constitute Variations And How To Evaluate Them? |
| 27 | MBJ 1st Vol 2009 | What Are Preliminaries and How to Evaluate Them? |
| 28 | MBJ 2nd Vol 2009 | What is Force Majeure and can it include Price Escalation? |
| 29 | MBJ 3rd Vol 2009 | What is the difference between Patent and Latent Defects? |
| 30 | MBJ 4th Vol 2009 | When is the Contractor Responsible and Liable for Defects? |
| 31 | MBJ 1st Vol 2010 | Effective Risk Management - Enhancing Value in Managing Projects? |
| 32 | MBJ 2nd Vol 2010 | What is Fit for Purpose and its Implication? |
| 33 | MBJ 3rd Vol 2010 | Can the Contractor's Employment be Determined Upon Substantial Completion? |
| 34 | MBJ 4th Vol 2010 | What is Head Office Overheads? |
| 35 | MBJ 1st & 2nd Vol 2011 | What are Expedition, Mitigation and Acceleration? |
| 36 | MBJ 3rd Vol 2011 | Ground Conditions - Mysteries Unraveled |
| 37 | MBJ 4th Vol 2011 | Design and Builder Contracts - Implications and Limitations |
| 38 | MBJ 2nd Vol 2012 | The Need For Planning and Programming in Construction |
| 39 | MBJ 3rd Vol 2012 | The Proper Preparation and Use of Works Programme in Construction |
| 40 | MBJ 4th Vol 2012 | Managing Construction Risks |
| 41 | MBJ 1st & 2nd Vol 2013 | Is Global Claim Dead or Still Alive? |
| 42 | MBJ 2013 - 2014 | The Impending Demise of Conditional Payment Clauses in the Malaysian Construction Industry (Part 1, 2 & 3) |
| 43 | MBJ 3rd Vol 2014 | Rates Rationalization Practices in the Construction Industry |
| 44 | MBJ 1st & 2nd Vol 2015 | An Update on Additional Preliminaries Evaluation (Part 1 & 2) |
| 45 | MBJ 1st Vol 2016 | Introducing Dispute Resolution Advisor (“DRA”) System to Overcome Disputes in Malaysia |
| 46 | MBJ 2nd Vol 2016 | What does Progressing with Works Regularly and Diligently mean? |
| 47 | MBJ 3rd Vol 2016 | What are Inclement Weather Claims? |
| 48 | MBJ 4th Vol 2016 | Condition Precedent – Issues and Implications |
| 49 | MBJ 1st Vol 2017 | The Importance of Being Insured Adequately for Construction Works |
| 50 | MBJ 2nd-4th Vol 2017 | Subcontracting - Issues and Implications (Part 1 to Part 3) |
| 51 | MBJ 1st Vol 2018 | Time at Large – Issues and Implications |
| 52 | MBJ 2nd Vol 2018 | S-Curve - Issues and Implications |
| 53 | MBJ 3rd Vol 2018 | Set-offs - A Revisit and Updates |
| 54 | MBJ 4th Vol 2018 | PAM Contract 2018 - Changes and Implications |
| 55 | MBJ 1st-4th Vol 2019 | Essential of Progress Reporting in Construction Industry |
| 56 | MBJ 1st & 3rd Vol 2020 | Delay Analysis - Which Method Preferred? |
| 57 | MBJ 2nd Vol 2020 | Covid-19 ~ Time & Monetary Claims, Entitlement and Evaluation |
| 58 | MBJ 1st Vol 2021 | Liquidated and Ascertained Damages (LAD) in Construction Contracts |
| 59 | Malaysian Surveyor 2020 | Coronavirus or Covid-19 ~ A Force Majeure Event |
| 60 | CIDB Heights 2021 | Covid-19 - Time & Monetary Claims, Entitlement and Evaluation |
| 61 | MBJ 2nd & 3rd Vol 2021 | Mediation – The Better Alternative for Construction Dispute Resolution in Malaysia? |
| 62 | MBJ 1st Vol 2022 | Expert Determination - The Potential ADR Route for the Malaysian Construction Industry? |
| 63 | MBJ 1st Vol 2023 | Updates on Inclement Weather Claims |
| 64 | MBJ 3rd Vol 2023 | Measuring Construction Progress |
| 65 | MBJ 2nd Vol 2024 | Physical & Financial Performance Measures in Construction |
Table of Contents
More Articles
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 13, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
Can a contractor claim for compensation for extra work when there is no S.O. instruction?
Read More »
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 12, 2022
No Comments
May 9, 2022
No Comments
Is Final Account Final? If not, What are the
Circumstances that Allow Revisions to be made?
Read More »
April 7, 2022
No Comments
April 7, 2022
No Comments
April 7, 2022
No Comments
April 7, 2022
No Comments
April 7, 2022
No Comments
April 7, 2022
No Comments
April 7, 2022
No Comments
Can the Contractor Insist on Agreeing to the Cost of Variation Work Before He Proceeds With It?
Read More »
April 7, 2022
No Comments
December 15, 2021
No Comments
December 15, 2021
No Comments
December 15, 2021
No Comments
December 15, 2021
No Comments